May 14th  2020 - Datacenter

Aqua Ray's data centre construction site: planning

Aqua Ray datacenter - Timeline
Certification
Stages of completion Forecast date
Uptime Institute Thesis Writing May 2020
Technical exchanges, Tier IV certification approvals July 2020
ISO27001 / HDS procedures update November 2020
ISO27001 / HDS audit and certification May 2021
Construction
Stages of completion Forecast date
Structure Study March 2020
Removing pre-existing partitions January 2020
Firewall installation 1h February 2020
1hr firewall doubling on pre-existing wall March 2020
Fire door installation 30 minutes March 2020
Floor treatment, paint April 2020
Ramp Construction May 2020
Interstage slab drilling April 2020
Electricité
Stages of completion Forecast date
Closure Study March 2020
Delivery / MES generators March 2020
Generator connection (channel A) April 2020
New Elec 2 room (Track B) May 2020
ENEDIS Arrival Diversion May 2020
Generator connection (track B) May 2020
B-track commissioning June 2020
Renovation room Elec 1 (lane A) July 2020
Testing, consuel and MES of 2 ways August 2020
Climatisation
Stages of completion Forecast date
Closure Study March 2020
Reception of new chassis Blocks April 2020
Installation of the new Blocks May 2020
Roof drilling, cross-bracing and waterproofing April 2020
Laying DC-level networks May 2020
Laying the floor and roof networks June 2020
Tests, and MES July 2020
Systèmes contrôle d'accès
Stages of completion Forecast date
Closure Study May 2020
Internal door control badge installation June 2020
Intruder Detector Installation July 2020
Multi-staff SAS installation August 2020
Systèmes Anti-Incendie
Stages of completion Forecast date
Closure Study April 2020
Leak tests June 2020
Installation of detectors type VESDA June 2020
Non-Chemical Gas Extinguishing Installation June 2020
Tests, and MES August 2020

Did you like this article? You might also like

Oct
2023

Aqua Ray launches construction of its third computer room

Datacenter

To make our services more accessible and meet growing demand, we are building an affordable IT colocation room for AI-related HPC workloads.

Continue
June
2020

Aurora IVY1: Air conditioning and cooling systems

Datacenter

Discover the different steps in the choice of cooling systems for our new data center with Tier 4 design: Aurora IVY1.

Continue
Oct
2023

Aqua Ray launches construction of its third computer room

Datacenter

To make our services more accessible and meet growing demand, we are building an affordable IT colocation room for AI-related HPC workloads.

Continue
June
2020

Aurora IVY1: Air conditioning and cooling systems

Datacenter

Discover the different steps in the choice of cooling systems for our new data center with Tier 4 design: Aurora IVY1.

Continue
Oct
2023

Aqua Ray launches construction of its third computer room

Datacenter

To make our services more accessible and meet growing demand, we are building an affordable IT colocation room for AI-related HPC workloads.

Continue
June
2020

Aurora IVY1: Air conditioning and cooling systems

Datacenter

Discover the different steps in the choice of cooling systems for our new data center with Tier 4 design: Aurora IVY1.

Continue
Need assistance? Call us now!
Call us now! 01 84 04 04 05
Call us now! 01 84 04 04 05
DC Tier IV
AFNOR Certification ISO27001
AFNOR Certification HDS